This project began with a simple goal: create meaningful, cost-effective housing on an existing Boise property. To make that happen, DSC had to work through zoning limits, parking requirements, and square footage restrictions before designing and building a solution that met both the client’s needs and the City’s requirements.
  • Our Role

    Design and Build

  • Year

    2024-2025

  • Location

    Boise, ID

Details

The 626 Brookman ADU project started with a client who wanted to add a meaningful living space to her property and create more affordable housing for her community. While the property had enough physical space for a detached ADU, the path to approval was much more complicated than it first appeared. DSC was brought in to guide both the design and build process, helping the client work through code requirements, site constraints, design revisions, and budget adjustments to find a path forward.

One of the biggest challenges was the existing detached garage. It had been built in the early 1950s on the property line, which meant it could not realistically be modified without triggering setback issues. Removing that structure made the most sense, but doing so created a new problem: the project still had to satisfy Boise’s off-street parking requirements for an ADU. At the same time, the size of the existing primary residence created another major limitation. Because Boise code limited a detached ADU to 900 square feet or 70 percent of the size of the primary residence, whichever was less, the client’s 800-square-foot home only allowed for a 560-square-foot ADU. That was far short of what was needed to make the project functional.

DSC and the client worked through multiple design rounds trying to solve these issues. Different approaches were explored, including revisions to the ADU layout, attempts to reduce the program to fit within the smaller detached size limit, and alternate configurations intended to satisfy the code requirements. Each option helped clarify the path, but none fully solved the problem on its own. This project required persistence, careful reading of the municipal code, and ongoing communication with the City of Boise Planning Department.

The breakthrough came when DSC identified a better strategy: add an attached garage to the primary residence in a way that would satisfy off-street parking needs while also increasing the square footage of the main home. DSC brought that interpretation forward to the City and worked directly through the approval process until the approach was confirmed. That single decision changed the project. It allowed the client to move forward with a design that met her full needs list rather than settling for an undersized compromise.

As the design evolved, the budget also had to be revisited. The revised solution increased the scope beyond the original early ballpark, so DSC worked through value-engineering adjustments to keep the project aligned as closely as possible with the client’s comfort range while still preserving the features that mattered most. In the end, the

Project Brief
  • Location

    Boise, ID

  • scope

    ADU w/ attached garage addition to primary residence

  • timeline

    3 Months Design, 3 Months permitting, 6 Months Build

  • client goal

    Build an ADU so she could provide some cost-effective living space for her community.

The Challenge

The challenge on this project was not a lack of space on the property, but a combination of code and site constraints that made a straightforward ADU difficult to approve. The existing detached garage was built on the property line, which meant modifying it was not practical under current setback requirements. Removing it solved one issue, but created another by affecting the off-street parking required for an ADU. On top of that, Boise’s size limit for detached ADUs meant the client’s 800-square-foot primary residence would only allow a 560-square-foot ADU, far smaller than what the client needed. DSC and the client worked through multiple rounds of design revisions trying to solve these overlapping issues while also keeping the project aligned with budget expectations.

Our Solution

The solution came through persistence, code study, and creative problem-solving. DSC identified that adding an attached garage to the primary residence could solve the parking issue while also increasing the square footage of the main home. After further discussion with the City of Boise and review of the municipal code, that approach was approved. This opened the door to a design that better fit the client’s goals and allowed the ADU to move forward in a way that satisfied both practical needs and code requirements. Once the design path was confirmed, DSC worked through budget updates and value-engineering adjustments to keep the project feasible. The result was a completed ADU that fulfilled the client’s vision and created new living space with lasting value for both the property and the community.

Project Images

Customer Review

Helen Brookman
Almost a full year, from concept to finished project, and it was all so worth it! It was a very collaborative process, and I’m so happy with my new space. It was especially great to know I was helping support so many small businesses, and families. Derek and all the subs were like extended family.

Similar Projects

The client wanted to create a dedicated woodshop for retirement while also including comfortable living space for visiting family. Because workshop dust and guest living areas usually need to be separated, the project required thoughtful planning and detailing. DSC helped bring both functions together under one roof in a way that was practical, durable, and award-winning.
During covid ADU’s became very popular in downtown Boise. Covid had produced a remote work culture that was allowing many people to travel and still remotely perform their responsibilities. The clients on this project wanted to invest some of their savings to build an ADU that they could list on short term rental websites. Since this lot was near Quinn’s Pond and the Boise Whitewater Park the new ADU easily took the name, “The Wave House”.